PRE-SCREENING STAGE
(0 DAY)
- Submission of Application for Permit-In-Principle.
- Calculation of Permit Processing Fees and Issuance of Bill.
- Payment of Permit Processing Fees by the Applicant Into designated Ogun State Government Account.
ACCEPTANCE STAGE.
(DAY 1-2)
- Submission of Evidence of Payment of Permit-In-Principle Processing Fees and the required Documents
Read More
PROCESSING STAGE.
(DAY 3-5)
- SSER Review
- Vetting and Recommendation by Recommending Officer
- Recommendation by Head of Department.
APPROVAL STAGE.
(DAY 6-7)
- Endorsement by Permanent Secretary.
- Clearance by The Honourable Commissioner.
- Issuance of Permit in Principle Letter.
PRE-SCREENING STAGE
(0 DAY)
- Submission of Application for Planning Information
- Payment Of Processing Fee for Planning Information by the Applicant Into designated Ogun State Government Account.
ACCEPTANCE STAGE.
(DAY 1-3)
- Submission of Evidence of Payment of Planning Information Processing Fees and the Following Documents:
- Detailed Site Location Plan
- Sun Print Survey Plan (Optional)
- Satellite Imagery of Subject Site
- Project Brief
- Site Inspection & Report Writing.
PROCESSING STAGE.
(DAY 4)
- Recommendation by Head of Department.
APPROVAL STAGE.
(DAY 5)
- Clearance by Permanent Secretary
- Issuance of Planning Information Letter.