PRE-SCREENING STAGE
(0 DAY)
- Checking of Architectural Plan.
- Checking of Structural Plan.
- Checking of Other Plans.
- Calculation of Permit Processing Fees and Issuance of Bill.
- Payment of Permit Processing Fees by the Applicant Into designated Ogun State Government Account.
ACCEPTANCE STAGE.
(DAY 1-2)
- Submission of Evidence of Payment of Permit Processing Fees and the Following Documents:
Read More
PROCESSING STAGE.
(DAY 3-5)
- Charting (Where Necessary)
- SSER Review
- Vetting and Recommendation by Recommending Officer
- Confirmation of Payment of Permit Processing Fee
- Stamping & Sealing of Plans
APPROVAL STAGE.
(DAY 6-7)
- Permit Granted by ZTPO.
- Issuance & Collection of Building Permit.