PRE-SCREENING STAGE
(0 DAY)
- Submission of Application for Land Use Clearance with the Following Documents
Read More
PROCESSING STAGE 1.
(DAY 1-3)
- Site Inspection & Report.
- Registration of Application
- PPAR Review
- Vetting by Recommending Officer.
- Issuance of Bill for Layout Permit Processing Fee and Submission of Evidence of Payment of Same.
- Recommendation by Head of Department.
LUC PERMIT STAGE.
(DAY 4-7)
- Endorsement by Permanent Secretary.
- Clearance by The Honourable Commissioner.
- Issuance of Land Use Clearance Permit.