PRE-SCREENING STAGE
(0 DAY)

  • Submission of Application for Land Use Clearance with the required Documents




Read More




PROCESSING STAGE 1.
(DAY 1-3)

  • Site Inspection & Report.
  • Registration of Application
  • PPAR Review
  • Vetting by Recommending Officer.
  • Issuance of Bill for Permit Processing Fee and Submission of Evidence of Payment of Same.
  • Recommendation by Head of Department.

LUC PERMIT STAGE.
(DAY 4-7)

  • Endorsement by Permanent Secretary.
  • Clearance by The Honourable Commissioner.
  • Issuance of Land Use Clearance Permit.




SUBMISSION STAGE.
(DAY 8)

  • Submission of Evidence of Payment of Permit Processing Fees and the required Documents to the Zonal Town Planning Office.



Read More

PROCESSING STAGE II
(DAY 9-11)

  • Site Inspection & Report Writing. (Where Applicable)
  • Vetting by Recommending Officer.
  • Confirmation of Payment of Permit Processing Fee
  • Stamping & Sealing of Plans
  • Recommendation by ZTPO

BUILDING PERMIT APPROVAL.
(DAY 12-14)

  • Endorsement by H.O.D
  • Clearance by General Manager
  • Issuance of Building Permit by ZTPO.