PRE-SCREENING STAGE
(0 DAY)

  • Submission of Application for Provisional Layout Permit with the Following Documents

Read More









PROCESSING STAGE 1.
(DAY 1-4)

  • Site Inspection & Report.
  • Registration of Application
  • PPAR Review
  • Vetting by Recommending Officer.
  • Issuance of Bill for Layout Permit Processing Fee and Submission of Evidence of Payment of Same.
  • Recommendation by Head of Department.


LUC PERMIT STAGE.
(DAY 5-7)

  • Endorsement by Permanent Secretary.
  • Clearance by The Honourable Commissioner.
  • Issuance of Provisional Layout Permit.






PRE-SCREENING STAGE
(0 DAY)

  • Submission of Application for Optic Fibre/Gas Pipeline Right-of-Way Permit with the Following Documents
  • Evidence of Payment of Registration Fee
  • Two (2) Hard Copies of the Optics Fibre/Gas Pipeline Route Alignment Plan Drawn on A0 Paper
  • Certificate of Incorporation from Corporate Affairs Commission (C.A.C) (If proponent is a Company / Organization)
  • Raster/Satellite Imagery of Subject Site Showing the Route Alignment

PROCESSING STAGE.
(DAY 1-4)

  • Site Inspection & Report Writing.
  • Vetting of Route by Recommending Officer.
  • Issuance of Bill for Right-of- Way Permit Processing Fee and Submission of Evidence of Payment of Same.
  • Recommendation by Head of Department.









RIGHT-OF-WAY PERMIT STAGE.
(DAY 5-7)

  • Endorsement by Permanent Secretary.
  • Clearance by The Honourable Commissioner.
  • Issuance of Optic Fibre/Gas Pipeline Right-of-Way Permit.